COORDINATION OF THE INSTALLATION SCHEDULE
Installation schedule must be coordinated with the overall construction schedule.
CRITICAL EXAMINATION AND TESTING IN ACCORDANCE WITH REGULATIONS
After a contract is placed and the installation is complete, the installer, in conjunction with a RSO, has to undertake a critical examination in accordance with regulations.
The critical examination is to ensure that the safety features and warning devices incorporated into the equipment are operating correctly and that there is sufficient protection of the staff, visitors and patients awaiting diagnosis or treatment against unnecessary exposure to ionizing radiation. A critical examination is appropriate when there could be radiation protection implications associated with the incorrect installation, such as the failure of the safety features or warning devices to operate correctly, poor siting or inadequate shielding. Although this requirement is concerned primarily with radiation protection aspects that affect staff and visitors, the safety features and warning devices may be relevant to patient safety as well. It requires an examination of the manner in which the equipment is erected and installed. An experienced surveyor selectively examining those features, which are most likely to affect safety can achieve this, and then to probe more deeply depending on the results obtained.
Often, the customer's RSO or Medical Physicist on behalf of the installer undertakes the critical examination.
client should not allow the equipment to be used for medical exposures unless the results of the critical examination are satisfactory.
ACCEPTANCE TESTING (HAND OVER BY THE CONTRACTOR AND BY THE OEM)
Acceptance is then undertaken by a representative of the client to verify that the contractor has supplied all the equipment specified and has performed adequate tests to demonstrate that the specified requirements in the contract have been met. The onus is on the contractor to undertake the tests. Client can contract out this work to OEM or this work can be done in combination with client Maintenance, BME and OEM. In any case, confusion must be avoided by identifying responsible individuals. Acceptance may be a matter of simply completing a checklist. Any significant discrepancy should be notified formally to the contractor, who is required to undertake corrective action. Mechanical and electrical safety tests are required in addition to radiation safety tests. During testing, Medical Physicist, BME, and Facility Planing work with OEM and in an organized way.
COMMISSIONING BY MEDICAL PHYSICIST
Commissioning is a set of tests carried out by the purchaser's representative to ensure that the equipment is ready for clinical use and to establish baseline values against which the results of subsequent routine performance tests can be compared. An important objective at this stage is to help confirm that the requirements of regulations are being met.
Some of the commissioning tests take the form of checks and measurements and may have already been included in the critical examination undertaken by the installer or the OEM. Duplication can be avoided if the installer and the surveyor undertaking the commissioning undertake these tests jointly. The opportunity can then be taken to take corrective action, if necessary, so that the performance of the imaging system is optimized, which is the other purpose of commissioning. After major work on the equipment, the relevant commissioning tests may have to be repeated to establish new baseline values, for example, after an X-ray tube is replaced.
One Medical Physicist may undertake the critical examination, acceptance and commissioning. Although the tests may be combined, their purpose should remain distinct.
ROUTINE PERFORMANCE TESTING
Routine performance (or constancy) testing comprises those tests, which are undertaken either regularly, or after maintenance or repairs, to detect whether any change in the performance of the equipment has occurred; if so, corrective action can be initiated. Routine performance tests are in effect a sub-set of the commissioning tests.
Generally, routine performance testing will involve both internal and external staff. Internal staff necessarily undertakes the frequent tests, which are quick to perform. External staff undertakes the more time-consuming tests, which may require special expertise and instrumentation. As many of these tests have implications for radiation safety, they are usually undertaken under the auspices of the user's radiation protection adviser. This also provides a measure of independence from the user and the maintenance contractor. The service engineer, medical physicist or other external agency may also undertake the tests. A collaborative, multi-disciplinary approach to routine performance testing is essential.